South Terminal Arrivals Extension, Gatwick Airport

Client:
ROK

Fire Shield Project Value:
£675,000

The Development:
The construction of a large extension to the existing South Terminal Arrivals Hall, including new baggage belts and the re-configuration the existing baggage area.

Fire Shield Scope of Works:

  • Firestopping to service penetrations through walls and floors
  • Acoustic sealing
  • Promat 15mm Promatect P250 combined with 120mm thick Rockwool RW3 Insulation to provide the required Fire Protection and Thermal Insulation
  • Promat 15mm P250 Board to provide Fire Protection to structural steelwork
  • Hilti Fixings and Unistrut Hangers to provide a support framework for Mechanical and Electrical Services